Transpower says contractor Omexom is working through its own recommendations after the June pylon topple that caused a power outage in Northland. Â
An Electricity Authority report found bad practice that caused the Transpower tower to topple had probably happened before. Â
Unsupervised, inexperienced maintenance crews from contractor Omexom unfastened three legs at once. Â
Transpower Executive General Manager Mark Ryall told Mike Hosking you do need to be able to train people on the job, otherwise they'll never become competent. Â
But he says a trainee needs to be under direct supervision, and in this case they weren't adequately supervised.Â