Mayor sees ‘light at the end of the tunnel’ as first train runs through $5.5b CRL

Author
Bernard Orsman,
Publish Date
Thu, 13 Feb 2025, 1:31pm

Mayor sees ‘light at the end of the tunnel’ as first train runs through $5.5b CRL

Author
Bernard Orsman,
Publish Date
Thu, 13 Feb 2025, 1:31pm
  • The first test train has completed its journey through the $5.5 billion City Rail Link.
  • Auckland Mayor Wayne Brown called the test “momentous,” highlighting progress toward improved public transport.
  • The City Rail Link will increase rail capacity and reduce congestion when it opens in 2026.

The first test train has completed its first trip through the full length of the $5.5 billion City Rail Link - two months late.

Auckland Infrastructure director Barry Potter told the Herald last year the first test train was set to run in early December. Former CRL boss Dr Sean Sweeney also said the aim was to run the first train by the end of 2024.

Despite the late running of the first trial service, politicians today praised the historic moment for the mammoth project, which began construction in 2016, faced cost blowouts, and is due to come into service for passengers next year.

Last night, a three-carriage train left Waitematā station at 9pm and took two-and-a-half hours to complete its first 3.4km journey under central Auckland past the new underground stations at Te Waihorotiu and Karanga-a-Hape to Maungawhau Station on the western line.

The speed was deliberately slow, about 5km/h, allowing technicians to complete their first round of underground checks and balances relating to tunnel clearance, power supply, and signalling.

The first train at the new Karanga-a-Hape undergroiund station last night.
The first train at the new Karanga-a-Hape undergroiund station last night.

Getting the green signal to proceed came after exhaustive planning and safety checks that peaked last week when the tunnels’ overhead electricity lines went live to power trains.

Auckland Mayor Wayne Brown called the test service “momentous”, saying after the project’s share of challenges it’s good to see progress toward a better public transport system delivering benefits for Aucklanders.

“I’ve always said I was determined to get the project finished and over the line, and we can finally see the light at the end of the tunnel,” he said.

Transport Minister Chris Bishop said what started under the previous National Government, the CRL will double Auckland’s rail capacity and reduce congestion when it opens in 2026, enabling Aucklanders to get to where they want to go quickly and safely meaning a more productive Auckland.

“There is still a lot more work to do, but it’s great to see measurable progress being made on-site as we countdown to the CRL opening next year,” he said.

Transport Minister Chris Bishop. Photo / Mark Mitchell
Transport Minister Chris Bishop. Photo / Mark Mitchell

When the CRL opens, patronage will rise from 15,000 passengers per hour to 27,000, but more costly work is needed on the rail network, including removing rail crossings and lengthening platforms for nine-car carriages, to run at a maximum capacity of 54,000 passengers an hour during peak times.

Minister of Auckland Simeon Brown said the CRL will be a game-changer for Auckland’s public transport network, turning Britomart from a dead-end station into a through station, enhancing connections between the central city and the wider rail network.

Bevan Assink, KiwiRail’s programme director for the CRL, said the test trial confirms that trains and the CRL infrastructure can seamlessly integrate with the wider KiwiRail network.

The City Rail Link promises "More trains, faster times" when it opens in 2026.
The City Rail Link promises "More trains, faster times" when it opens in 2026.

He said tests will accelerate in the coming weeks, including brake testing on one of the steepest sections of railway in New Zealand, recovery procedures, and the start of hands-on training for drivers.

“The start of CRL dynamic testing in the tunnels closely follows another key milestone - the successful completion of KiwiRail’s latest stage of its network upgrade programme,” Assink said.

CRL Ltd chief executive Patrick Brockie said it was made clear last November that the first train was not on a critical path and a later running of the first train has no impact on the programme.

CRL Ltd is due to hand over the CRL in November this year to Auckland Transport for further testing before it opens to passengers sometime in 2026.

The CRL’s original cost was between $2b and $3b and was expected to be completed in 2023-24.