Auckland rush hour trains delayed, Onehunga line suspended

Author
NZ Herald,
Publish Date
Thu, 4 Jul 2024, 8:02am
A logging truck has tipped blocking SH2 with logs.
A logging truck has tipped blocking SH2 with logs.

Auckland rush hour trains delayed, Onehunga line suspended

Author
NZ Herald,
Publish Date
Thu, 4 Jul 2024, 8:02am

There is more chaos on Auckland’s train network as city-bound trains are blocked from Britomart and services have been delayed while trains on the Onehunga line have been suspended.

According to Auckland Transport (AT), trains on the Southern, Western and Eastern lines are operating at a 20-minute reduced frequency and are terminating at Newmarket and the Strand.

A van connection was available between the two points and “customers can also use bus Route 70, 75 and Innerlink from Newmarket”.

While services on the Onehunga Line have been suspended.

AT said customers could use bus routes 30 or 309 and scheduled buses are accepting rail tickets.

AT said a track infrastructure issue at Britomart is to blame for the rush hour disruption.

KiwiRail General Manager Metros Jon Knight said about 6.50am they lost signals detection at a set of points, which allow trains to switch between tracks, in the approach to Britomart Station.

“Because of where the points are, no trains are currently able to enter Britomart. Southern and Western Line services are ending at Newmarket and Eastern Line services at The Strand,” he said.

“Our signals staff are on site. They are currently working on the issue and will aim to fix it as quickly as they can.”